Projects

Repair Hangar 6 Building Systems All Projects

BME teamed with Coleman Construction and Washington Engineering on this design-build project. The project had multiple challenges. Replacement of the high voltage and low voltage distribution systems was necessary, while maintaining the facility at full functioning capacity. BME used multiple generators to power three substations feeding the hangar while installing new equipment and cable. Testing and commissioning had to be performed before energizing.

Project Size Project Location
$750K - $1M Naval Air Station Whidbey Island, Oak Harbor WA